Over 300ha of site clearance (includes approx 5000 trees)
Over 2,000 amphibians, including 587great crested newts, 488 smooth newts, 885 toads and 103 frogs, trapped and moved
42km of fencing complete
10 km of drainage installed so far
20 Drainage lagoons created
50 Utility service diversions changed over or ready
High Pressure gas main diversion completed
512,000 cubic metres of topsoil strip
1.2 million cubic metres of bulk excavation
11,507t of material so far used for structures, compounds, piling mats, crane platforms
56,000 cubic metres of site-won gravels stockpiled for surface construction
2,354 cubic metres of concrete in place
New Drayton Lane – Earthworks and utility service diversions complete.
Green Lane West/Wroxham Rd junction
Progress on cycleways, bridleways and paths – being completed as mainline works and roundabouts progress
Over 500,000 hours recorded without a LTA (Lost Time Accident)